2. (10 points) Below is an earned value analysis (EVA) chart for a construction project. Determine the status of the project. Is the project ahead
2. (10 points) Below is an earned value analysis (EVA) chart for a construction project. Determine the status of the project. Is the project ahead or behind the schedule? Is the project over budget or under budget? (Note: BCWP: budgeted cost of work performed, ACWP: Actual cost of work performed, and BCWS: budgeted cost of work scheduled) WH/Cost 50 WH BCWP = 39 ACWP = 35 32 = BCWS Study Date Time