2 . ( 2 5 Points ) Using discrete available - to - promise ( ATP ) logic, calculate the master production schedule ( MPS

2.(25 Points) Using discrete available-to-promise (ATP) logic, calculate the master production schedule (MPS) for the following conditions.
On hand Period
12345
Forecast 2018251512
Orders 64803
Projected available balance 15
Available-to-promise (discrete)
Master production schedule
Lot size =25, Safety stock =10

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Basics Of Health Care Performance Improvement A Lean Six Sigma Approach

Authors: Donald Lighter

1st Edition

0763772143, 978-0763772147

More Books

Students also viewed these General Management questions

Question

Explain the influences on demand Explain the influences on supply

Answered: 1 week ago