2 9 . Considering the impact of both schedule and cost performance; what the entire project is likely to cost is expressed by ? TCPI

29. Considering the impact of both schedule and cost performance; what the entire project is
likely to cost is expressed by?
TCPI =(BAC EV)/(BAC-AC)
Estimate to Complete (ETC)=(BAC EV)/ CPI
Estimate at completion (EAC)= AC +(BAC EV)/(CPI X SPI)
Estimate at completion (EAC )= BAC / CPI
30. What is the TCPI of the project based on following project data? (1) EAC = $115,000(2)
BAC = $100,000,(3) EV = $25,000(4) AC = $40,000.
0
1
-1
.5
31. Considering the following project data what is the Estimate at Completion (EAC) if the
work is performed at the budgeted rate? BAC = $22,000 EV = $13,000 PV = $14,000 AC =
$15,000
$24,000
$14,000
$15,000
$22,000
32. A project is experiencing cost over run. What is true about Cost Performance Index (CPI)
CV is equal to 1
CPI is greater than 1
CPI is less than 1
CPI is equal to 1
33. A project has a budget of $30,000 and the costs incurred till date is $20,000. The project
has achieved $10,000 worth of work. The project manager believes that the future work will
progress at the planned rate. What is the Estimate at Completion (EAC) of the project?
$40,000
$20,000
$30,000
$10,000
34. The planned value of task A is $150,000 and task B is $500,000. After six months the
project manager does a performance analysis of the project and finds that the project is
behind schedule. The actual cost incurred in completing task A is $175,000 and that for
completing 80% of task B is $650,000. What is the cost performance index of the project?
0.67
0.96
1.66
0.76
35. Earned Value (EV) minus Planned Value (PV) is
Cost Variance (CV)
Schedule Performance Index (SPI)
Cost Performance Index (CPI)
Schedule Variance (SV)
36. SPI less than one implies that
Project performance is as per the baseline plan
Project is behind schedule
Project is ahead of schedule
Planned Value (PV) is less than Earned Value (EV

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Contemporary Logistics

Authors: Paul R. Murphy, Michael Knemeyer

11th edition

132953463, 2900132953466, 978-0132953467

More Books

Students also viewed these General Management questions

Question

What is one result of the Single European Act

Answered: 1 week ago