Answered step by step
Verified Expert Solution
Question
1 Approved Answer
2 9 . Considering the impact of both schedule and cost performance; what the entire project is likely to cost is expressed by ? TCPI
Considering the impact of both schedule and cost performance; what the entire project is
likely to cost is expressed by
TCPI BAC EVBACAC
Estimate to Complete ETCBAC EV CPI
Estimate at completion EAC AC BAC EVCPI X SPI
Estimate at completion EAC BAC CPI
What is the TCPI of the project based on following project data? EAC $
BAC $ EV $ AC $
Considering the following project data what is the Estimate at Completion EAC if the
work is performed at the budgeted rate? BAC $ EV $ PV $ AC
$
$
$
$
$
A project is experiencing cost over run. What is true about Cost Performance Index CPI
CV is equal to
CPI is greater than
CPI is less than
CPI is equal to
A project has a budget of $ and the costs incurred till date is $ The project
has achieved $ worth of work. The project manager believes that the future work will
progress at the planned rate. What is the Estimate at Completion EAC of the project?
$
$
$
$
The planned value of task A is $ and task B is $ After six months the
project manager does a performance analysis of the project and finds that the project is
behind schedule. The actual cost incurred in completing task A is $ and that for
completing of task B is $ What is the cost performance index of the project?
Earned Value EV minus Planned Value PV is
Cost Variance CV
Schedule Performance Index SPI
Cost Performance Index CPI
Schedule Variance SV
SPI less than one implies that
Project performance is as per the baseline plan
Project is behind schedule
Project is ahead of schedule
Planned Value PV is less than Earned Value EV
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started