Question
2. A crew comprising of 5 laborers, 1 operator, 0.5 labor foreman is observed to take 5 days (40 hours) to excavate 2,000 CY
2. A crew comprising of 5 laborers, 1 operator, 0.5 labor foreman is observed to take 5 days (40 hours) to excavate 2,000 CY of heavy soil. If the wage rate of laborers is $20.00/hour, foreman are $35.00/hour, and operators are $44/hour, find the unit cost of labor for excavation for this project. (5 Points)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
To find the unit cost of labor for excavation for this project we can follow these steps 1 Calcu...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get StartedRecommended Textbook for
Managerial Economics and Business Strategy
Authors: Michael R. baye
7th Edition
978-0073375960, 71267441, 73375969, 978-0071267441
Students also viewed these General Management questions
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
View Answer in SolutionInn App