Question

1 Approved Answer

2. A project has seven activities. Partial crashing is available. Normal Crash Normal Time Cost Time (weeks) ($) (weeks) 4 3,000 3 9 5,000


image

2. A project has seven activities. Partial crashing is available. Normal Crash Normal Time Cost Time (weeks) ($) (weeks) 4 3,000 3 9 5,000 7 4 7,000 4 6 6,000 4 8 4,000 3 4,000 4 2,000 Activity A B C D E F G Immediate Predecessors none A A B, C C D E, F 622 Crash Cost ($) 5,000 8,000 7,000 8,000 8,000 9,000 7.000 asilo MO oaO MOM Maximum Weeks Reduced 1 2 0 2 2 1 2 (a) What is the expected project completion time? (b) What is the critical path? (c) What activities should be crashed and how much will they cost to reduce the completion time of the project by three weeks?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

To address the questions a To find the expected project completion time well first calculate the ear... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Cambridge International AS & A Level Further Mathematics Coursebook

Authors: Lee Mckelvey, Martin Crozier

1st Edition

1108403379, 978-1108403375

More Books

Students also viewed these General Management questions

Question

A curve, C, has polar equation r =2 - sin , for 0 2. Sketch C.

Answered: 1 week ago

Question

Determine the integral 25 - 9 -2 dx.

Answered: 1 week ago

Question

Refer to Exercise

Answered: 1 week ago