2. Cost Flows As of the end of October, the job cost sheets at Detroit Scooters, Inc., show the following total costs accumulated on three custom jobs. Job 918 Job 920 e 3 4 Direct materials Direct labor Overhead applied Job 919 17,500 8,700 5,220 43,250 19,500 11.700 19,500 14,200 8,520 Job 918 was started in production in September and the following costs were assigned to it in September: direct materials, $5,600; direct labor, $1,200; and overhead, $720. Jobs 919 and 920 were started in October. Overhead cost is applied with a predetermined rate based on direct labor cost. Jobs 918 and 919 were finished in October, and Job 920 is expected to be finished in November. No raw materials were used indirectly in October. Using this information, answer the following questions. The company's predetermined overhead rate was the same for the entire year. 8. Instructions: 182. Complete the table below to calculate the cost of the raw materials requisitioned and direct labor cost incurred during October for each of the three jobs? Direct Materials Problem Problem 2 Problem Problem Instructions: 1&2. Complete the table below to calculate the cost of the raw materials requisitioned and direct labor cost incurred during October for each of the three jobs? Direct Materials September October Job Total 918 919 920 Total 30 31 Job 32 Direct Labor September October Total 85 Tota 3. Using the accumulated costs of the jobs. what predetermined overhead rate is used? Problem Problem 2. Problem 3 Problem 4 3. Using the accumulated costs of the jobs, what predetermined overhead rate is used? Overhead Rate Numerator Denominator Overhead Rate Job Total 49 Job 50 Overhead September October 23 3 333333333 3 13233555 TASR 33333333333333333 52 53 Total 54 4. How much total cost is transferred to finished goods during June? Direct Applied Job Direct Labor Total Cost Materials Overhead 58 9 181 59919- 60920 61 Total - Problem 1 Problem 2 Problem pro