Question

1 Approved Answer

2 . Create a resource loading table and perform resource leveling on the project composed of the activities in this table. You may use Excel

2. Create a resource loading table and perform resource leveling on the project composed of the
activities in this table. You may use Excel for your convenience.
Activity Duration
(days)
Amount of
hours/day Total hours Predecessor
A 6636--
B 11010--
C 2816 A
D 41040 B
E 188 C, D
F 188 E
G 6848 E
H 3824 F
I 2816 F
J 3824 G, H, I
K 5840 J
L 3824 K
a) Construct the project network diagram.
b) Identify the ES, EF, LS, LF, float and the critical path.
c) Create a Time-Phased Resource Loading Table for this project, identifying the activity early
start and late finish points in the table
d) Assume that the maximum amount of time used per day is 16 hours. With this resources
usage limitations, can you identify any weeks with resource over commitments?
e) Resource level the loading table. Identify the activity that can be rescheduled and
reconfigure the table to show this reallocation.Create a resource loading table and perform resource leveling on the project composed of the activities in this table. You may use Excel for your convenience.
\table[[Activity,\table[[Duration],[(days)]],\table[[Amount of],[hours/day]],Total hours,Predecessor],[A,6,6,36,--],[B,1,10,10,--],[C,2,8,16,A],[D,4,10,40,B],[E,1,8,8,C, D],[F,1,8,8,E],[G,6,8,48,E],[H,3,8,24,F],[I,2,8,16,F],[J,3,8,24,G, H, I],[K,5,8,40,J],[L,3,8,24,K]]
a) Construct the project network diagram.
b) Identify the ES, EF, LS, LF, float and the critical path.
c) Create a Time-Phased Resource Loading Table for this project, identifying the activity early start and late finish points in the table
d) Assume that the maximum amount of time used per day is 16 hours. With this resource's usage limitations, can you identify any weeks with resource over commitments?
e) Resource level the loading table. Identify the activity that can be rescheduled and reconfigure the table to show this reallocation.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The General Model Of Working Capital Management

Authors: Rodrigo Zeidan

1st Edition

9811933332, 978-9811933332

More Books

Students also viewed these General Management questions

Question

Recognize the causes of listening breakdown.

Answered: 1 week ago

Question

What is its position?

Answered: 1 week ago

Question

What are the organizations relationship goals on this issue?

Answered: 1 week ago