2 . Create a resource loading table and perform resource leveling on the project composed of the activities in this table. You may use Excel
Create a resource loading table and perform resource leveling on the project composed of the
activities in this table. You may use Excel for your convenience.
Activity Duration
days
Amount of
hoursday Total hours Predecessor
A
B
C A
D B
E C D
F E
G E
H F
I F
J G H I
K J
L K
a Construct the project network diagram.
b Identify the ES EF LS LF float and the critical path.
c Create a TimePhased Resource Loading Table for this project, identifying the activity early
start and late finish points in the table
d Assume that the maximum amount of time used per day is hours. With this resources
usage limitations can you identify any weeks with resource over commitments?
e Resource level the loading table. Identify the activity that can be rescheduled and
reconfigure the table to show this reallocation.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started