2 days 4 days 1 day 2 days p | AcCt. 2 Act. 1 T | Act.5 |>| Act. 6 5 days 1 day 2
2 days 4 days 1 day 2 days p | AcCt. 2 Act. 1 T | Act.5 |>| Act. 6 5 days 1 day 2 days Act. 7 Act. 3 Act. 4 The PM wants to reduce the duration of this project to 9 days. If no activity could be crashed more than 1 day and the cost of crashing per time unit is: Act. 1 200 Act. 2 150 Act. 3 NA Act. 4 250 Act. 5 MNA Act. 180 Act. 7 350 To reduce the duration to 9 days, the cost of crashing is: ) 1050 ) 950 ) 700 () 7RO