2. Draw product structure diagram for final product. Prepare MRP for component B. Child Items Lead time Current Inventory Final product A (3 required)
2. Draw product structure diagram for final product. Prepare MRP for component B. Child Items Lead time Current Inventory Final product A (3 required) 1 week 25 B (2 required) C (2 required) A B (3 required) 1 week none C (1 required) B none 2 weeks 200 C none 1 week none The MPS for final product: Week Number Quantity 1 0 20 0 MO 3 0 47 5 6 75 100 125