Answered step by step
Verified Expert Solution
Link Copied!

Question

00
1 Approved Answer

2. Earned-value analysis. A project budget calls for the following expenditures: Task Date Budgeted Amount Build forms April 1 $10,000 April 1 $50,000 Pour foundation

2. Earned-value analysis. A project budget calls for the following expenditures:

Task Date Budgeted Amount
Build forms April 1 $10,000
April 1 $50,000
Pour foundation May 1 $100,000
May 1 $30,000
Frame walls June 1 $30,000

Remaining tasks

July 1 and beyond $500,000

Define each term in your own words, calculate these values for the above project, and show your work:

  1. Budgeted cost baseline (make a graph illustrating this one)
  2. Budget at completion (BAC)
  3. Planned value (PV) as of May 1
  4. Earned value (EV) as of May 1 if the foundation work is only two-thirds Everything else is on schedule.
  5. SV as of May
  6. Actual cost as of May 1 is $160,000. Calculate the cost variance (CV) as of May
  7. Schedule performance index (SPI)
  8. Cost performance index (CPI)
  9. Estimate to complete (ETC), assuming that the previous cost variances will not affect future costs
  10. Estimate at completion (EAC)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Microeconomics An Intuitive Approach with Calculus

Authors: Thomas Nechyba

1st edition

538453257, 978-0538453257

Students also viewed these General Management questions

Question

Let x = 0.99999 .... (a) Do you think that x Answered: 1 week ago

Answered: 1 week ago