[2 marks] Describe the different types of responses to unfavorable project risks. 2. [10 marks]The information of Project ABCis given in the table below. Calculate
- [2 marks] Describe the different types of responses to unfavorable project risks.
2. [10 marks]The information of Project ABCis given in the table below. Calculate the weighted average time and the variance of each activity. Identify the critical path(s) and the expected project duration by using PERT. What is the probability of completing the project in 55 days?
Activity ID | Predecessor | Optm. (a) (Days) | Most Likely (m) (Days) | Pess. (b) (Days) |
A | None | 6 | 12 | 24 |
B | A | 16 | 19 | 28 |
C | A | 4 | 7 | 10 |
D | A | 21 | 30 | 39 |
E | C | 13 | 22 | 37 |
F | B,E,D | 4 | 7 | 10 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started