[2 marks] Describe the different types of responses to unfavorable project risks. 2. [10 marks]The information of Project ABCis given in the table below. Calculate

  1. [2 marks] Describe the different types of responses to unfavorable project risks.

2. [10 marks]The information of Project ABCis given in the table below. Calculate the weighted average time and the variance of each activity. Identify the critical path(s) and the expected project duration by using PERT. What is the probability of completing the project in 55 days?

Activity

ID

Predecessor

Optm. (a)

(Days)

Most Likely (m)

(Days)

Pess. (b)

(Days)

A None 6 12 24
B A 16 19 28
C A 4 7 10
D A 21 30 39
E C 13 22 37
F B,E,D 4 7 10

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managing Hospitality Human Resources

Authors: Robert H Woods, Educational Institute Staff American Hotel & Lodging Association

4th Edition

0866122877, 9780866122870

More Books

Students also viewed these General Management questions

Question

=+b) Are the conditions for ANOVA met? Why or why not?

Answered: 1 week ago

Question

Always show respect for the other person or persons.

Answered: 1 week ago