Answered step by step
Verified Expert Solution
Question
1 Approved Answer
2) Please see below table : Duration Predecessor Lag Activity Code A B Total budget 7000 6000 7 3 A -2 Activity Description Design Site
2) Please see below table : Duration Predecessor Lag Activity Code A B Total budget 7000 6000 7 3 A -2 Activity Description Design Site Mobilization Excavation Foundation Structure ID -1 D E 10 16 20 C -6 10000 8000 10000 B D F 15 14 mm -6 -5 -10 4500 2800 G Painting Heating system Wiring H 8 2400 F G H Commissioning 2 2000 2-1 )Draw network and do forward & backward path and show critical path (20) 2-2 )Which activity has the maximum float (10) 2-3) If you want to decrease the project duration for 5 days, what will be your suggestion ( assume that the cost for decreasing duration is the same for all activities and for each activity you can just cut 2 days) (10) 2-4) Draw the Gantt chart of the project (10) 3) consider the above project, we are at the end of month 10 and we finish design, site mobilization and 45% excavation. And for all these tasks we spent $25,540. Please draw PV, EV and AC curve and show the EAC with 3 different ways (optimistic, Most likely, pessimistic) (30) 2) Please see below table : Duration Predecessor Lag Activity Code A B Total budget 7000 6000 7 3 A -2 Activity Description Design Site Mobilization Excavation Foundation Structure ID -1 D E 10 16 20 C -6 10000 8000 10000 B D F 15 14 mm -6 -5 -10 4500 2800 G Painting Heating system Wiring H 8 2400 F G H Commissioning 2 2000 2-1 )Draw network and do forward & backward path and show critical path (20) 2-2 )Which activity has the maximum float (10) 2-3) If you want to decrease the project duration for 5 days, what will be your suggestion ( assume that the cost for decreasing duration is the same for all activities and for each activity you can just cut 2 days) (10) 2-4) Draw the Gantt chart of the project (10) 3) consider the above project, we are at the end of month 10 and we finish design, site mobilization and 45% excavation. And for all these tasks we spent $25,540. Please draw PV, EV and AC curve and show the EAC with 3 different ways (optimistic, Most likely, pessimistic) (30)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started