2. Project Monitoring (Earned Value Analysis): You have been given a project to make 1,000 units of colouring pens over 50 days. You planned to

2. Project Monitoring (Earned Value Analysis): You have been given a project to make 1,000 units of colouring pens over 50 days. You planned to produce ata steady rate of 25 pens per day. The budget cost per pen is 50p. The total project budget is 500. At the end of day 10 you have made 130 pens at a cost of 95 (AC). {Total 30 marks}

a. Calculate the Planned Value (PV) and the Earned Value [5 Marks] (EV) of the project

b. Calculate the Schedule Variance (SV) and the Schedule [5 Marks] performance index (SP!)

c. Calculate the Cost Variance (CV) and the Cost [10 Marks] performance index (CPI)

d. Calculate and explain the Estimate at Completion (EAC) [10 Marks]

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Payroll Accounting 2022

Authors: Bernard J. Bieg, Judith A. Toland

32nd Edition

0357518756, 9780357518755

More Books

Students also viewed these Accounting questions

Question

Case : Karl and June Monroe

Answered: 1 week ago

Question

4.3 Describe the job analysis process and methods.

Answered: 1 week ago