2 Summerlin Company budgeted 4,500 pounds of material costing $4.00 per pound to produce 2,500 units. The company actually used 5,000 pounds that cost $4.10
2 Summerlin Company budgeted 4,500 pounds of material costing $4.00 per pound to produce 2,500 units. The company actually used 5,000 pounds that cost $4.10 per pound to produce 2,500 units. What is the direct materials quantity variance? 2 Multiple Choice points $450 unfavorablee $500 unfavorable. $2,500 unfavorable $2,050 unfavorable. $2,000 unfavorable