2. The company just informed you that a competitor may have been working on a similar product. They have asked you to crash the project.

2. The company just informed you that a competitor may have been working on a similar product. They have asked you to crash the project. The associated indirect costs based on the projects duration are: $11,000 for 12 weeks, $8,000 for 11 weeks, $4,500 for 10 weeks, $4,000 for 9 weeks, and $3,500 for 8 weeks. The following table summarizes the cost of crashing your project by activity. a) Use the least cost method and reduce the schedule until you reach the crash point of the network. For each move, identify what activity(s) was(were) crashed, the adjusted total cost, and explain your choices. b) What is the optimum cost-time schedule for the project? What is the cost? c) c) Draw the Cost-Duration Graph in graphing grid below or in MS Excel.

  1. The company just informed you that a competitor may have been working on a similar product. They have asked you to crash the project. The associated indirect costs based on the projects duration are: $11,000 for 12 weeks, $8,000 for 11 weeks, $4,500 for 10 weeks, $4,000 for 9 weeks, and $3,500 for 8 weeks. The following table summarizes the cost of crashing your project by activity.
    1. Use the least cost method and reduce the schedule until you reach the crash point of the network. For each move, identify what activity(s) was(were) crashed, the adjusted total cost, and explain your choices.
    2. What is the optimum cost-time schedule for the project? What is the cost?
    3. c) Draw the Cost-Duration Graph in graphing grid below or in MS Excel.
Normal
ID Crash Cost Max. crash time Time Cost
A 0 0 2 4,000
B 0 0 1 1,500
C 2,000 1 3 6,000
D 0 0 1 3,000
E 2,500 1 2 8,000
F 5,000 1 3 12,000
G 3,000 1 2 5,000
H 4,000 1 2 1,500
Total 41,000

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals Of Project Management

Authors: James P. Lewis

3rd Edition

0814408796, 978-0814408797

More Books

Students also viewed these General Management questions

Question

1. Try oral, open-book, or group tests.

Answered: 1 week ago

Question

To what microcultural groups do you belong?

Answered: 1 week ago