$200,000 Wages $100,000 Disposal $50,000 Supplies $350,000 Total Activity Cost Pools Remove Galvanized Pipe Job Setup Other Wag as 65% 25% 1 0% Disposal 75%
$200,000 Wages $100,000 Disposal $50,000 Supplies $350,000 Total Activity Cost Pools Remove Galvanized Pipe Job Setup Other Wag as 65% 25% 1 0% Disposal 75% 25% 0% Supplies 60% 20% 20%