22. A agreed to build a house for B with payment for the house to be made...
Fantastic news! We've Found the answer you've been seeking!
Question:
22. A agreed to build a house for B with payment for the house to be made on completion. After A had completed some of the work, A breached the contract by abandoning it, and in return B rescinded the contract. Can A claim remuneration for the work done to date and damages for B's rescission of the contract?
Posted Date: