Answered step by step
Verified Expert Solution
Link Copied!

Question

...
1 Approved Answer

22. LOOK AT THE CALENDAR SCREEN IN MS PROJECT FOR THIS ANSWER: Microsoft Project uses multiple calendars for its scheduling engine. WHICH of the following

22. LOOK AT THE CALENDAR SCREEN IN MS PROJECT FOR THIS ANSWER: Microsoft Project uses multiple calendars for its scheduling engine. WHICH of the following is the default (standard) project calendar setting for all new MS Project plans?

A.M-F 6AM-6PM

B.M-S 8AM-5PM

C.M-F 8AM-5PM

D.S-S 8AM-10PM

23.You might make a working time adjustment to your project calendar to accommodate a company-wide picnic that everyone, including the project team, is encouraged to attend.

TRUE

FALSE

24. You should always schedule a project plan in MS Project FROM the start date and not the finish date because of which of the following?

A.It causes all tasks to start as late as possible

B.It causes all tasks to start as soon as possible

C.It gives you the least amount of flexibility, so the project will stay on time better

D.None of the other answers are true--you should always schedule from the finish date

E.All of the other answers, combined, are true

25.The Advanced Properties dialog box contains all of the following properties for a project plan EXCEPT:

A.Project manager name

B.Project Calendar

C.Subject of project

D.Company name

E.Title for project

26.The duration of 2ed is equal to WHICH of the following hours?

A.8 hours

B.36 hours

C.24 hours

D.48 hours

E.16 hours

F.2 hours

27.The Finish-to-start relationship is accurately described as WHICH of the following?

A.The start date of the predecessor task determines the start date of the successor task.

B.The finish date of the predecessor task determines the finish date of the successor task.

C.The start date of the predecessor task determines the finish date of the successor task.

D.The finish date of the predecessor task determines the start of the successor task.

28.Which of the following scheduling methods should be used to fully take advantage of MS Project's powerful scheduling engine?

A.Manual scheduling

B.Finish-to-start scheduling

C.Automatic scheduling

D.Trial scheduling

29.Which of the following is NOT an appropriate name for a milestone?

A.Foundation inspection is approved

B.Vehicle packed

C.Set up supplies

D.Kickoff meeting completed

30.The duration for automatically scheduled tasks can never be any value other than 1d.

TRUE

FALSE

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

College Physics Reasoning and Relationships

Authors: Nicholas Giordano

2nd edition

978-0840058195

Students also viewed these General Management questions