22. Marigold Corp. is constructing a building. Construction began January 1, 2017 and the building was completed 12/31/17. Marigold made payments to the construction company
22. Marigold Corp. is constructing a building. Construction began January 1, 2017 and the building was completed 12/31/17. Marigold made payments to the construction company of $2,994,000 on 7/1, $6,216,000 on 9/1, and $5,910,000 on 12/31. Weighted-average accumulated expenditures were
A. $3,569,000
B. $9,210,000
C. $15,120,000
D. $3,044,000