Question
23. Blossom Construction Co. contracted to build a bridge for $11,800,000. Construction began in 2021 and was completed in 2022. Data relating to the construction
23.
Blossom Construction Co. contracted to build a bridge for $11,800,000. Construction began in 2021 and was completed in 2022. Data relating to the construction are:
2021 | 2022 | |||
Costs incurred during the year | $3,894,000 | $3,236,000 | ||
Estimated costs to complete | 3,186,000 |
Blossom uses the percentage-of-completion method.
1. How much revenue should be reported for 2021?
Revenue | $ |
2. Make the entry to record progress billings of $4,100,000 during 2021. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is required, select "No Entry" for the account titles and enter 0 for the amounts.)
Account Titles and Explanation | Debit | Credit |
3. Make the entry to record the revenue and gross profit for 2021. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is required, select "No Entry" for the account titles and enter 0 for the amounts.)
Account Titles and Explanation | Debit | Credit |
4. How much gross profit should be reported for 2022?
Gross profit | $ |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started