Question
24-1A Bumblebee Company estimates that385,800direct labor hours will be worked during the coming year, 2017, in the Packaging Department. On this basis, the budgeted manufacturing
Bumblebee Company estimates that385,800direct labor hours will be worked during the coming year, 2017, in the Packaging Department. On this basis, the budgeted manufacturing overhead cost data are computed for the year.
Fixed Overhead Costs | Variable Overhead Costs | ||
Supervision | $91,080 | Indirect labor | $185,184 |
Depreciation | 74,520 | Indirect materials | 100,308 |
Insurance | 24,840 | Repairs | 61,728 |
Rent | 22,560 | Utilities | 57,870 |
Property taxes | 17,880 | Lubricants | 30,864 |
$230,880 | $435,954 |
It is estimated that direct labor hours worked each month will range from28,700to39,200hours.
During October,28,700direct labor hours were worked and the following overhead costs were incurred.
Fixed overhead costs: Supervision $7,590, Depreciation $6,210, Insurance $2,015, Rent $1,880, and Property taxes $1,490.
Variable overhead costs: Indirect labor $14,756, Indirect materials, $7,042, Repairs $4,532, Utilities $4,725, and Lubricants $2,596.
(a)Prepare a monthly manufacturing overhead flexible budget for each increment of3,500direct labor hours over the relevant range for the year ending December 31, 2017.(List variable costs before fixed costs.)
BUMBLEBEE COMPANY Packaging Department Monthly Manufacturing Overhead Flexible Budget For the Year 2017 | ||||
Activity LevelDepreciationDirect LaborDirect Labor HoursDirect MaterialsFixed CostsIndirect LaborIndirect MaterialsInsuranceLubricantsProperty TaxesRentRepairsSupervisionTotal CostsTotal Fixed CostsTotal Variable CostsUtilitiesVariable Costs | ||||
Activity LevelDepreciationDirect LaborDirect Labor HoursDirect MaterialsFixed CostsIndirect LaborIndirect MaterialsInsuranceLubricantsProperty TaxesRentRepairsSupervisionTotal CostsTotal Fixed CostsTotal Variable CostsUtilitiesVariable Costs | ||||
Activity LevelDepreciationDirect LaborDirect Labor HoursDirect MaterialsFixed CostsIndirect LaborIndirect MaterialsInsuranceLubricantsProperty TaxesRentRepairsSupervisionTotal CostsTotal Fixed CostsTotal Variable CostsUtilitiesVariable Costs | ||||
Activity LevelDepreciationDirect LaborDirect Labor HoursDirect MaterialsFixed CostsIndirect LaborIndirect MaterialsInsuranceLubricantsProperty TaxesRentRepairsSupervisionTotal CostsTotal Fixed CostsTotal Variable CostsUtilitiesVariable Costs | $ | $ | $ | $ |
Activity LevelDepreciationDirect LaborDirect Labor HoursDirect MaterialsFixed CostsIndirect LaborIndirect MaterialsInsuranceLubricantsProperty TaxesRentRepairsSupervisionTotal CostsTotal Fixed CostsTotal Variable CostsUtilitiesVariable Costs | ||||
Activity LevelDepreciationDirect LaborDirect Labor HoursDirect MaterialsFixed CostsIndirect LaborIndirect MaterialsInsuranceLubricantsProperty TaxesRentRepairsSupervisionTotal CostsTotal Fixed CostsTotal Variable CostsUtilitiesVariable Costs | ||||
Activity LevelDepreciationDirect LaborDirect Labor HoursDirect MaterialsFixed CostsIndirect LaborIndirect MaterialsInsuranceLubricantsProperty TaxesRentRepairsSupervisionTotal CostsTotal Fixed CostsTotal Variable CostsUtilitiesVariable Costs | ||||
Activity LevelDepreciationDirect LaborDirect Labor HoursDirect MaterialsFixed CostsIndirect LaborIndirect MaterialsInsuranceLubricantsProperty TaxesRentRepairsSupervisionTotal CostsTotal Fixed CostsTotal Variable CostsUtilitiesVariable Costs | ||||
Activity LevelDepreciationDirect LaborDirect Labor HoursDirect MaterialsFixed CostsIndirect LaborIndirect MaterialsInsuranceLubricantsProperty TaxesRentRepairsSupervisionTotal CostsTotal Fixed CostsTotal Variable CostsUtilitiesVariable Costs | ||||
Activity LevelDepreciationDirect LaborDirect Labor HoursDirect MaterialsFixed CostsIndirect LaborIndirect MaterialsInsuranceLubricantsProperty TaxesRentRepairsSupervisionTotal CostsTotal Fixed CostsTotal Variable CostsUtilitiesVariable Costs | ||||
Activity LevelDepreciationDirect LaborDirect Labor HoursDirect MaterialsFixed CostsIndirect LaborIndirect MaterialsInsuranceLubricantsProperty TaxesRentRepairsSupervisionTotal CostsTotal Fixed CostsTotal Variable CostsUtilitiesVariable Costs | ||||
Activity LevelDepreciationDirect LaborDirect Labor HoursDirect MaterialsFixed CostsIndirect LaborIndirect MaterialsInsuranceLubricantsProperty TaxesRentRepairsSupervisionTotal CostsTotal Fixed CostsTotal Variable CostsUtilitiesVariable Costs | ||||
Activity LevelDepreciationDirect LaborDirect Labor HoursDirect MaterialsFixed CostsIndirect LaborIndirect MaterialsInsuranceLubricantsProperty TaxesRentRepairsSupervisionTotal CostsTotal Fixed CostsTotal Variable CostsUtilitiesVariable Costs | ||||
Activity LevelDepreciationDirect LaborDirect Labor HoursDirect MaterialsFixed CostsIndirect LaborIndirect MaterialsInsuranceLubricantsProperty TaxesRentRepairsSupervisionTotal CostsTotal Fixed CostsTotal Variable CostsUtilitiesVariable Costs | ||||
Activity LevelDepreciationDirect LaborDirect Labor HoursDirect MaterialsFixed CostsIndirect LaborIndirect MaterialsInsuranceLubricantsProperty TaxesRentRepairsSupervisionTotal CostsTotal Fixed CostsTotal Variable CostsUtilitiesVariable Costs | ||||
Activity LevelDepreciationDirect LaborDirect Labor HoursDirect MaterialsFixed CostsIndirect LaborIndirect MaterialsInsuranceLubricantsProperty TaxesRentRepairsSupervisionTotal CostsTotal Fixed CostsTotal Variable CostsUtilitiesVariable Costs | ||||
Activity LevelDepreciationDirect LaborDirect Labor HoursDirect MaterialsFixed CostsIndirect LaborIndirect MaterialsInsuranceLubricantsProperty TaxesRentRepairsSupervisionTotal CostsTotal Fixed CostsTotal Variable CostsUtilitiesVariable Costs | $ | $ | $ | $ |
(b)Prepare a flexible budget report for October.(List variable costs before fixed costs.)
BUMBLEBEE COMPANY Packaging Department Manufacturing Overhead Flexible Budget Report For the Month Ended October 31, 2017 | ||||
Difference | ||||
Budget | Actual Costs | Favorable Unfavorable Neither Favorable nor Unfavorable | ||
Activity LevelDepreciationDirect LaborDirect Labor HoursDirect MaterialsFixed CostsIndirect LaborIndirect MaterialsInsuranceLubricantsProperty TaxesRentRepairsSupervisionTotal CostsTotal Fixed CostsTotal Variable CostsUtilitiesVariable Costs | ||||
Activity LevelDepreciationDirect LaborDirect Labor HoursDirect MaterialsFixed CostsIndirect LaborIndirect MaterialsInsuranceLubricantsProperty TaxesRentRepairsSupervisionTotal CostsTotal Fixed CostsTotal Variable CostsUtilitiesVariable Costs | ||||
Activity LevelDepreciationDirect LaborDirect Labor HoursDirect MaterialsFixed CostsIndirect LaborIndirect MaterialsInsuranceLubricantsProperty TaxesRentRepairsSupervisionTotal CostsTotal Fixed CostsTotal Variable CostsUtilitiesVariable Costs | $ | $ | $ | FavorableUnfavorableNeither Favorable nor Unfavorable |
Activity LevelDepreciationDirect LaborDirect Labor HoursDirect MaterialsFixed CostsIndirect LaborIndirect MaterialsInsuranceLubricantsProperty TaxesRentRepairsSupervisionTotal CostsTotal Fixed CostsTotal Variable CostsUtilitiesVariable Costs | FavorableUnfavorableNeither Favorable nor Unfavorable | |||
Activity LevelDepreciationDirect LaborDirect Labor HoursDirect MaterialsFixed CostsIndirect LaborIndirect MaterialsInsuranceLubricantsProperty TaxesRentRepairsSupervisionTotal CostsTotal Fixed CostsTotal Variable CostsUtilitiesVariable Costs | FavorableUnfavorableNeither Favorable nor Unfavorable | |||
Activity LevelDepreciationDirect LaborDirect Labor HoursDirect MaterialsFixed CostsIndirect LaborIndirect MaterialsInsuranceLubricantsProperty TaxesRentRepairsSupervisionTotal CostsTotal Fixed CostsTotal Variable CostsUtilitiesVariable Costs | FavorableUnfavorableNeither Favorable nor Unfavorable | |||
Activity LevelDepreciationDirect LaborDirect Labor HoursDirect MaterialsFixed CostsIndirect LaborIndirect MaterialsInsuranceLubricantsProperty TaxesRentRepairsSupervisionTotal CostsTotal Fixed CostsTotal Variable CostsUtilitiesVariable Costs | FavorableUnfavorableNeither Favorable nor Unfavorable | |||
Activity LevelDepreciationDirect LaborDirect Labor HoursDirect MaterialsFixed CostsIndirect LaborIndirect MaterialsInsuranceLubricantsProperty TaxesRentRepairsSupervisionTotal CostsTotal Fixed CostsTotal Variable CostsUtilitiesVariable Costs | FavorableUnfavorableNeither Favorable nor Unfavorable | |||
Activity LevelDepreciationDirect LaborDirect Labor HoursDirect MaterialsFixed CostsIndirect LaborIndirect MaterialsInsuranceLubricantsProperty TaxesRentRepairsSupervisionTotal CostsTotal Fixed CostsTotal Variable CostsUtilitiesVariable Costs | ||||
Activity LevelDepreciationDirect LaborDirect Labor HoursDirect MaterialsFixed CostsIndirect LaborIndirect MaterialsInsuranceLubricantsProperty TaxesRentRepairsSupervisionTotal CostsTotal Fixed CostsTotal Variable CostsUtilitiesVariable Costs | FavorableUnfavorableNeither Favorable nor Unfavorable | |||
Activity LevelDepreciationDirect LaborDirect Labor HoursDirect MaterialsFixed CostsIndirect LaborIndirect MaterialsInsuranceLubricantsProperty TaxesRentRepairsSupervisionTotal CostsTotal Fixed CostsTotal Variable CostsUtilitiesVariable Costs | FavorableUnfavorableNeither Favorable nor Unfavorable | |||
Activity LevelDepreciationDirect LaborDirect Labor HoursDirect MaterialsFixed CostsIndirect LaborIndirect MaterialsInsuranceLubricantsProperty TaxesRentRepairsSupervisionTotal CostsTotal Fixed CostsTotal Variable CostsUtilitiesVariable Costs | FavorableUnfavorableNeither Favorable nor Unfavorable | |||
Activity LevelDepreciationDirect LaborDirect Labor HoursDirect MaterialsFixed CostsIndirect LaborIndirect MaterialsInsuranceLubricantsProperty TaxesRentRepairsSupervisionTotal CostsTotal Fixed CostsTotal Variable CostsUtilitiesVariable Costs | FavorableUnfavorableNeither Favorable nor Unfavorable | |||
Activity LevelDepreciationDirect LaborDirect Labor HoursDirect MaterialsFixed CostsIndirect LaborIndirect MaterialsInsuranceLubricantsProperty TaxesRentRepairsSupervisionTotal CostsTotal Fixed CostsTotal Variable CostsUtilitiesVariable Costs | FavorableUnfavorableNeither Favorable nor Unfavorable | |||
Activity LevelDepreciationDirect LaborDirect Labor HoursDirect MaterialsFixed CostsIndirect LaborIndirect MaterialsInsuranceLubricantsProperty TaxesRentRepairsSupervisionTotal CostsTotal Fixed CostsTotal Variable CostsUtilitiesVariable Costs | FavorableUnfavorableNeither Favorable nor Unfavorable | |||
Activity LevelDepreciationDirect LaborDirect Labor HoursDirect MaterialsFixed CostsIndirect LaborIndirect MaterialsInsuranceLubricantsProperty TaxesRentRepairsSupervisionTotal CostsTotal Fixed CostsTotal Variable CostsUtilitiesVariable Costs | $ | $ | $ | FavorableUnfavorableNeither Favorable nor Unfavorable |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started