24.If actual costs are greater than standard costs, there is a(n) A. normal variance. B. unfavorable variance. C. favorable variance. D. error in the accounting

24.If actual costs are greater than standard costs, there is a(n)

A. normal variance.

B. unfavorable variance.

C. favorable variance.

D. error in the accounting system.