25. If you know that an activity on the critical path has a latest finish time of 12 weeks and the activity takes 5 weeks
25. If you know that an activity on the critical path has a latest finish time of 12 weeks and the activity takes 5 weeks to complete, then the earliest finish time is ________ weeks 12 7 19 Not enough information given 38. A project is in its 17th week and has just completed activity H. The total costs to complete the project through activity H was budgeted as $47,600. According to the project plan, activity H was to be completed by week 18. The actual costs incurred to complete the project through activity H was $52,100. Which of the following statements is true? The project is over budget but within the time schedule. The project is over budget and taking longer than specified on the schedule. The project is on budget and on schedule. There is not enough information to determine if the project is on schedule. 51. The traditional approach in project management is also referred to as the _________________ approach. Agile Extreme Scrum Waterfall 52. The project schedule is primarily used to determine all of the following except _______________ . cost estimates activity start times activity end dates slack times activity end dates
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started