29. A. During the construction of a recently completed project, your finish carpentry crew consisting of a journeyman and two laborers installed 24 interior
29. A. During the construction of a recently completed project, your finish carpentry crew consisting of a journeyman and two laborers installed 24 interior doors with hardware in six hours. Determine the production rate per person for the door and hardware installation on this project. Using the same crew size and production rate from above, how many days to install 72 doors?