29.30 Schedule of Activity Costs Quality Control Activities Activity Cost Process audits $49,300 Training of machine operators 28,100 Processing returned products 17,900 Scrap processing (disposal)
29.30
Schedule of Activity Costs |
Quality Control Activities | Activity Cost |
Process audits | $49,300 |
Training of machine operators | 28,100 |
Processing returned products | 17,900 |
Scrap processing (disposal) | 26,200 |
Rework | 8,700 |
Preventative maintenance | 27,900 |
Product design | 40,100 |
Warranty work | 7,900 |
Finished goods inspection | 22,700 |
From the above schedule of activity costs, determine the prevention costs.
a.$96,100
b.$56,000
c.$114,000
d.$104,800
--------------
Schedule of Activity Costs |
Quality Control Activities | Activity Cost |
Process audits | $49,400 |
Training of machine operators | 25,400 |
Processing returned products | 18,400 |
Scrap processing (disposal) | 24,100 |
Rework | 7,900 |
Preventative maintenance | 29,500 |
Product design | 42,200 |
Warranty work | 7,600 |
Finished goods inspection | 22,900 |
From the above schedule of activity costs, determine the value-added costs.
a.$169,400
b.$227,400
c.$146,500
d.$177,000
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started