. . 3 . 1 7 Thabo Mbeki, president of Mbeki Construction, has developed the tasks, durations, and predecessor relationships in the following table for

..3.17 Thabo Mbeki, president of Mbeki Construction, has developed the tasks, durations, and predecessor relationships in the following table for building new motels. Draw the AON network and answer the questions that follow.
\table[[Activity,\table[[Immediate],[Predecessor(s]],Time Estimates (in weeks)],[Optimisti,\table[[Most],[Likely]],Pessimistic],[A,+1,4,8,10],[B,A,2,8,24],[C,A,8,12,16],[D,A,4,6,10],[E,B,1,2,3],[F,E,C,6,8,20],[G,E,C,2,3,4],[H,F,2,2,2],[1,F,6,6,6],[I,D, G, H,4,6,12],[K,I. J,2,2,3]]
a) What is the expected (estimated) time for activity C??
b) What is the variance for activity C?
c) Based on the calculation of estimated times, what is the critical path?
d) What is the estimated time of the critical path?
e) What is the activity variance along the critical path?
f) What is the probability of completion of the project before week 36?
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Understanding Management

Authors: Richard L Daft, Dorothy Marcic

6th Edition

9780324581782, 324581785, 978-0324568387

More Books

Students also viewed these General Management questions

Question

3. Why did many early BPR efforts fail?

Answered: 1 week ago