Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

3 1 . The following production data were taken from the records of the finishing department for June: Inventory in process, June 1 , 2

31. The following production data were taken from the records of the finishing department for June:
Inventory in process, June 1,25% completed 500 units
Transferred to finished goods during June 4,600 units
Equivalent units of production during June 5,035 units
Determine the number of equivalent units of production in the June 30, finishing department inventory, assuming that the first-in, first-out method is used to cost inventories. The completion percentage of 25% applies to both direct materials and conversion costs.
a.840 units
b.672 units
c.560 units
d.448 units
32. Kaumajet Factory produces two products: table lamps and desk lamps. It has two separate departments: Fabrication and Assembly. The factory overhead budget for the Fabrication Department is $783,256, using 515,300 direct labor hours. The factory overhead budget for the Assembly Department is $698,112, using 86,400 direct labor hours.
If a table lamp requires 4 hours of fabrication and 7 hour of assembly, the amount of factory overhead that Kaumajet Factory will allocate to each unit of table lamp using the multiple production department factory overhead rate method with an allocation base of direct labor hours is
a. $188.59
b. $17.14
c. $8.08
d. $62.64
33. Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to four separate activity pools. The budgeted activity cost and activity base data by product are provided below.
Activity Cost
Activity Base
Procurement $374,700 Number of purchase orders
Scheduling 232,000 Number of production orders
Materials handling 490,800 Number of moves
Product development 791,200 Number of engineering changes
Production 1,498,000 Machine hours
Number of
Purchase
Orders
Number of
Production
Orders
Number
of
Moves
Number of
Engineering
Changes
Machine
Hours
Number
of
Units
Disk drives 3,8303301,220152,1001,800
Tape drives 1,70013580089,2004,100
Wire drives 11,8009503,9002811,1002,800
The activity rate for the scheduling activity cost pool is
a. $21.62 per production order
b. $66.88 per production order
c. $163.96 per production order
d. $264.81 per production order
34.
Dawson Company manufactures small table lamps and desk lamps. The following shows the activities per product and the total overhead information:
Units Setups Inspections Assembly (dlh)
Small table lamps 2,9003,1009,45040,800
Desk lamps 9,1006,20015,75040,800
Activity Total Activity-Base Usage Budgeted Activity Cost
Setups 9,300 $89,280
Inspections 25,200126,000
Assembly (dlh)71,400285,600
The total factory overhead to be allocated to desk lamps is
a. $301,470
b. $361,764
c. $542,646
d. $150,735
35.
The manufacturing costs of Calico Industries for three months of the year are provided below:
Total Cost Production (units)
April $111,100278,700
May 90,100169,400
June 103,300246,500
Using the high-low method, the variable cost per unit and the total fixed costs are
a. $3.42 per unit and $5,815
b. $0.19 per unit and $58,147
c. $0.34 per unit and $29,074
d. $1.90 per unit and $5,815
36.
Variable costs as a percentage of sales for Lemon Inc. are 72%, current sales are $549,000, and fixed costs are $197,000. How much will operating income change if sales increase by $46,500?
a. $13,020 decrease
b. $13,020 increase
c. $33,480 decrease
d. $33,480 increase
37.
If a business had sales of $3,769,000 and a margin of safety of 20%, the break-even point was
a. $4,522,800
b. $753,800
c. $3,015,200
d. $6,784,200
38. The debits to Work in ProcessAssembly Department for April, together with data concerning production, are as follows:
April 1, work in process:
Materials cost, 3,000 units $7,900
Conversion costs, 3,000 units, 80% completed 5,300
Materials added during April, 10,000 units 25,600
Conversion costs during April 33,000
Goods finished during April, 11,500 units
April 30, work in process, 1,500 units, 60% completed
All direct materials are placed in process at the beginning of the process, and the weighted average method is used to cost inventories.
The materials cost per equivalent unit (to the nearest cent) for April is
a. $2.58
b. $2.31
c. $2.91
d. $3.35
39. Aspen Technologies has the following budget data:
Estimated direct labor hours 8,900
Estimated direct labor dollars $54,400
Estimated factory overhead costs $179,900
If factory overhead is to be applied based on direct labor hours, the predetermined overhead rate is
a. $30.32
b. $16.17
c. $20.21
d. $24.26

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

College Accounting A Practical Approach 1-15

Authors: Jeffrey Slater

4th Edition

013142050X, 978-0131420502

More Books

Students also viewed these Accounting questions