3. (a) Fill out the following MRP record for Part C. Week Part C 1 2 3 4 5 6 Gross requirements 35 40

image text in transcribed

3. (a) Fill out the following MRP record for Part C. Week Part C 1 2 3 4 5 6 Gross requirements 35 40 40 40 40 50 Scheduled receipts 30 Projected available balance 40 Planned receipts Planned order releases Lot sizing method = FOQ(30); Leadtime = 1 week; Safety stock requirement = 0 unit (b) Given the above MRP record and the following routing data for Part C, determine the capacity requirements for work center 100 from Part C using CRP. For the scheduled receipt of 30 units in week 1, assume that the setup and half of the quantity have been completed. Routing Data for Part C Operation Operation 1 Work Center 100 Setup Time 2 hours Run Time 0.3 hour +Capacity requirements for work center 100 from Part C 1 Hours of Capacity 2 Week 3 4 5 6

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Essentials of Management

Authors: Andrew J. DuBrin

9th Edition

538478233, 2900538478235, 978-0538478236

More Books

Students also viewed these General Management questions

Question

Give eye contact, but do not stare.

Answered: 1 week ago