3. BU Contractors received a contract to construct an office building for $5,000,000. Construction was begun in 2021 and completed in 2023. BU has a
3. BU Contractors received a contract to construct an office building for $5,000,000. Construction was begun in 2021 and completed in 2023. BU has a calendar year end. Cost and other data are presented below:
2021 2022 2023
Cost Incurred during the year 1,100,000 2,800,000 700,000
Estimated costs to complete at 12/31 3,300,000 975,000
Billings during the year 1,500,000 2,700,000 800,000
Cash collections during the year 1,350,000 2,750,000 900,000
BU recognizes revenue over time according to percentage of completion.
Required: 1. Prepare all journal entries to record costs, billings, collections, and profit recognition. 2. Compute the Gross Profit on the job for each year.
3.Compute the ending Accounts Receivable for each year.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started