3 - Consider the project as outline in the tables below: c ) Assuming that the indirect cost is $ 8 0 0 0 ,
Consider the project as outline in the tables below:
c Assuming that the indirect cost is $ What is the total project cost after crashing?
NOTE: Total project cost after crashing Project duration after crashing indirect cost sigmasum of each activity time after crashing its normal costweek total crashing cost.
tableActivityPredecessor,tableNormal TimewkstableCrash TimewkstableNormalCost$wkCost to Crash $wkABACADBEBFCGD EH