Question
1 Approved Answer
3. During 2014, Gates Corp. started a construction job with a total contract price of $14,000,000. The job was completed on December 15, 2015. Additional
3. During 2014, Gates Corp. started a construction job with a total contract price of $14,000,000. The job was completed on December 15, 2015. Additional data are as follows:
2014 2015
Actual costs incurred during the year $5,400,000 $6,100,000
Estimated remaining costs 5,400,000
Billed to customer 4,800,000 9,200,000
Received from customer 4,000,000 9,600,000
Under the completed-contract method, what amount should Gates recognize as gross profit for 2015? SHOW WORK PLEASE
a. $900,000
b. $1,250,000
c. $1,900,000
d. $2,500,000
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started