Question
1 Approved Answer
3. Find the Critical Path(s) by calculating floats, (20 pts) Note: The Forward & Backward Pass results are given. The values are given within the
3. Find the Critical Path(s) by calculating floats, (20 pts) Note: The Forward & Backward Pass results are given. The values are given within the five- sided polygon, Forward Pass values point to the right and Backward Pass values to the left. H 13 A.2 D.S E.8 F.3 13 >