3 . ?In this exercise you must create / sketch a Current State Value Stream Map for the process described below. Use the basic symbols

3 . ?In this exercise you must create / sketch a Current State Value Stream Map for the process described below. Use
the basic symbols shown in the presentation and the text to depict each step. The company producing the part
is Huskie Metal Products.
- ?Product Information:
o Product is for an off - road vehicle and it is made from stamped metal with resistance welding
operations and assembly operations. The raw material is mild steel coil. The finished
product is shipped to the customer, ATV INC., on a daily basis.
- ?Production Control Information
o Huskie Metal Products ( HMP ) ?production control department receives the 3 0 / 6 0 / 9 0 ?day
forecast from ATV Inc. and enters into their ERP system. ATV Inc. also sends a DAILY order
to HMP s production control department.
o HMP electronically sends a 4 - week forecast to Steve s Steel Inc. ( SSI ) , ?who in turn delivers
steel coils on Monday and Wednesday each week.
o Production Control dept. creates a weekly schedule, and that weekly schedule is distributed
from the ERP system to each of the manufacturing processes in the line. The production
control department sends a daily shipping schedule to the shipping department.
- ?Process Steps and observations:
o Step 1 : 3 5 0 ?Ton Stamping Press with automatic feeding
? ?Observed inventory 4 ?days of coils BEFORE Press
? ?Cycle Time: 2 ?seconds per part
? ?One operator
o Step 2 : Auto - Tapper ?thread holes
? ?Observed inventory 2 . 5 ?days of parts BEFORE Auto - Tapper
? ?Cycle Time: 4 5 ?seconds per part
? ?One operator
o Step 3 : Press Brake ?fold into box shape
? ?Observed inventory 1 . 7 ?days of parts BEFORE Press Brake
? ?Cycle Time: 3 5 ?seconds per part
? ?One operator
o Step 4 : Resistance Weld
? ?Observed inventory 4 . 2 ?days of parts BEFORE Resistance Welder
? ?Cycle Time: 5 5 ?seconds per part
? ?One operator
o Step 5 : Assembly
? ?Observed inventory 3 . 5 ?days of parts BEFORE Assembly
? ?Cycle time: 7 5 ?seconds per part
? ?One operator
o Step 6 : Shipping
? ?Observed inventory 4 . 0 ?days of parts BEFORE Shipping
o Final Step: Finished parts shipped to ATV Inc. daily.
3 a ) ?Create / Sketch the Value Stream Map in its ?current state ( 1 0 ?pts each - 5 0 ?points total ) :
- ?Use correct symbols from book / presentation .
- ?Show inventory points where they belong with correct inventory levels.
- ?Show process data under each process.
- ?Show distribution of schedule information to each place it goes.
- ?Create the value added / wait cycle diagram under the manufacturing processes.
? 3 b ) ?Determine these values:
- ?What is the Production Lead Time? ( 1 0 ?points )
- ?What is the Total Processing Time? ( 1 0 ?points

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management Planning And Control Techniques

Authors: Rory Burke

3rd Edition

047198762X, 9780471987628

More Books

Students also viewed these General Management questions

Question

Relax your shoulders

Answered: 1 week ago

Question

Keep your head straight on your shoulders

Answered: 1 week ago