Question
3. MEYER WERFT HAS RECEIVED A CONTRACT FOR A LUXURY YACHT TO BE DELIVERED IN APRIL 2022. THE YACHT IS CONSTRUCTED FROM THE FOLLOWING SIX
3.MEYER WERFT HAS RECEIVED A CONTRACT FOR A LUXURY YACHT TO BE DELIVERED IN APRIL 2022. THE YACHT IS CONSTRUCTED FROM THE FOLLOWING SIX BLOCKS:
BLOCK 1(26 WEEKS)
BLOCK 2(15 WEEKS)
BLOCK 3(10 WEEKS)
BLOCK 4(5 WEEKS)
BLOCK 5(20 WEEKS)
BLOCK 6(5 WEEKS)
BLOCKS 1 & 2 ARE SEQUENTIAL. BLOCKS 3, 4, AND 5 CAN BE DONE ANYTIME IN ANY ORDER. HOWEVER, ONLY TWO OF THEM CAN BE UNDER CONSTRUCTION SIMULTANEOUSLY. BLOCKS 1-5 MUST BE COMPLETED BEFORE BLOCK 6 CAN BEGIN. THE OPTIMUM TIDES FOR GOING DOWN THE RIVER EMS ARE MARCH 15-18, 2022 AND SEPTEMBER 15-18, 2022.
MAKE A GANTT CHART FOR THE YATCH'S CONSTRUCTION
CONVERT YOUR GANTT CHART TO A PERT DIAGRAM
WHAT IS/ARE YOUR CRITICAL PATH(S)?
WHAT IS THE LATEST DATE CONSTRUCTION CAN BEGIN? IF YOU WANTED A TWO-WEEK CUSHION FOR UNFORESEEN PROBLEMS?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access with AI-Powered Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started