3. (TCO A) Blue Suede Construction Corp used the percentage-of-completion method of revenue recognition. They were contracted to build the new amphitheater for $800000. Additional
3. (TCO A) Blue Suede Construction Corp used the percentage-of-completion method of revenue recognition. They were contracted to build the new amphitheater for $800000. Additional information was provided:
As of Dec 31. 2012 2013
Percentage of completion 15% 40%
Estimated totalexpected costs $550,000 $580,000
Gross profit recognized (Cumulative) $50,000 $99,000
Contracted costs incurred during 2013 were(Points : 5)