3. The amount of time an activity can be delaved and vet not delay the project is termed A. Total slack B. Free slack C.
3. The amount of time an activity can be delaved and vet not delay the project is termed A. Total slack B. Free slack C. Critical float D. Float pad E. Slip pad 4. Jan is trying to reallocate resources in a time-constrained project to create smoother resource utilization with a low level of risk. She should look to activities with the A. Smallest duration B. Least slack C. Most slack D. Lowest identification number E. Highest cost