3. The data identified below was listed in a projects latest status report: a. PV = $36,000 b. EV = $30,000 c. AC = $33,000

3. The data identified below was listed in a projects latest status report: a. PV = $36,000 b. EV = $30,000 c. AC = $33,000 d. BAC = $120,000 e. Original length of the project 10 months

Using these data, calculate the following: a. What are the values for CPI and SPI? b. What is the expected cost at completion (EAC)? c. How much money will be needed from the time of the report to complete the project? d. What is the cost variance at completion (VAC)? e. Using SPI, what is the new expected length of the project?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Agile Project Management With Kanban

Authors: Eric Brechner

1st Edition

0735698953, 978-0735698956

More Books

Students also viewed these General Management questions

Question

What are the disadvantages of secondary data?

Answered: 1 week ago

Question

summarize the history of work psychology;

Answered: 1 week ago