Answered step by step
Verified Expert Solution
Question
1 Approved Answer
31) Use the values in the table to calculate activity durations and variances for the project. Which path is critical? How closely should the other
31) Use the values in the table to calculate activity durations and variances for the project. Which path is critical? How closely should the other path be watched and why? (5 marks) Predecessor Optimistic Activity Likely Pessimistic A 4 6 10 B A 2 5 8 C A 16 7 9 D B 3 9 20 E C 7 9 11 D,E 11 19
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started