32) Assume that a companys planned level of activity is 1,100 hours and its actual level of activity is 1,000 hours. Based on this information,
32) Assume that a companys planned level of activity is 1,100 hours and its actual level of activity is 1,000 hours. Based on this information, the companys activity variances for its fixed expenses will:
Multiple Choice
all be zero.
all be favorable.
all be unfavorable.
be favorable or unfavorable depending on each expenses cost behavior pattern.