32 During a presentation where projects are being considered, an analyst runs a model using all of the least favorable variables at the same time,

32 During a presentation where projects are being considered, an analyst runs a model using all of the least favorable variables at the same time, then, runs the model with the most favorable variables. We could call this

a. what if! Analysis

b. scenario analysis

c. sensitivity analysis

d. project comparative