Question

1 Approved Answer

32. The debits to Work in ProcessAssembly Department for May, together with data concerning production, are as follows: May 1, work in process: Materials cost,

32.

The debits to Work in ProcessAssembly Department for May, together with data concerning production, are as follows:

May 1, work in process:

Materials cost, 3,000 units $7,200
Conversion costs, 3,000 units, 66.7% completed 6,000
Materials added during May, 10,000 units 25,700
Conversion costs during May 30,700
Goods finished during May, 11,500 units 0
May 31 work in process, 1,500 units, 50% completed 0

All direct materials are placed in process at the beginning of the process and the first-in, first-out method is used to cost inventories. The materials cost per equivalent unit for May is

a.$2.23

b.$3.79

c.$3.07

d.$2.57

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Lease Audits The Essential Guide

Authors: Theodore H Hellmuth

1st Edition

0934055041, 978-0934055048

More Books

Students also viewed these Accounting questions

Question

Explain the nature of human resource management.

Answered: 1 week ago

Question

Write a note on Quality circles.

Answered: 1 week ago

Question

Describe how to measure the quality of work life.

Answered: 1 week ago