Question

1 Approved Answer

35. Lucas developed a project crashing data table for the I-80 repair project as shown below. The current estimated total cost for the project is

image text in transcribed

35. Lucas developed a project crashing data table for the I-80 repair project as shown below. The current estimated total cost for the project is $1,000,000. Indirect cost for the project is $10,000 per week. Use expected task times as normal times to answer questions and assume that there is no uncertainty for task times. 3. If Lucas would like to minimize the total project cost by crashing, (1) what is the project length after crashing? (2) what is the total project cost after crashing? 4. If Lucas would like to minimize the project duration by crashing as long as the total project cost does not exceed $1,000,000, (1) what is the project length after crashing? (2) what is the total project cost after crashing? 5. If Lucas would like to minimize the project duration by crashing, (1) what is the project length after crashing? (2) what is the total project cost after crashing

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managing Information Technology

Authors: Carol Brown, Daniel DeHayes, Jeffrey Hoffer, Wainright Marti

7th Edition

132146320, 978-0132146326

More Books

Students also viewed these General Management questions

Question

Unborn children: D may be liable for injuries inflicted on a fetus.

Answered: 1 week ago