Answered step by step
Verified Expert Solution
Question
1 Approved Answer
4. A construction project at day 70 has actual costs of $78,000 and a scheduled cost of $84,000. The Work Package Manager estimates a value
4. A construction project at day 70 has actual costs of $78,000 and a scheduled cost of
$84,000. The Work Package Manager estimates a value completed of $81,000.
Calculate SV & CV, CPI, and SPI. What does this tell you?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started