4)
a) Impressions Printing has four typesetters and four jobs to be completed as given in the table.The $ entries represent the firm's estimate of what it will cost for each job to be completed by each typesetter. Find the optimal assignment of jobs to typesetters so as to minimize the total costs.
Typesetters | ||||
Jobs | A | B | C | D |
R34 | $7 | $3 | $4 | $8 |
T50 | $5 | $4 | $6 | $5 |
S66 | $6 | $7 | $9 | $6 |
U70 | $8 | $6 | $7 | $4 |
b) Impressions Printing has the following printing jobs waiting to be processed at its work center. The jobs are assigned sequentially upon arrival. All dates are specified as days from today.
Jobs | Due Date | Duration (days) |
R34 | 43 | 10 |
T50 | 37 | 12 |
S66 | 34 | 11 |
U70 | 32 | 7 |
Z40 | 37 | 15 |
In what sequence should the firm process the jobs according to the SPT, EDD, and CR scheduling rules?