4. A project manager is using Project Network Diagram to perform critical path analysis. The diagram is
Fantastic news! We've Found the answer you've been seeking!
Question:
4. A project manager is using Project Network Diagram to perform critical path analysis. The diagram is represented as shown in Table 1
Activity number Activity name Duration in hours Predecessor Date/Location 2 Hotel booking 25 1 3 Arrival 15 4 On-site offers 20 On-site program 10 4 Send info to 6 2,3,4 participants 7 Approval 30 5,6 8 Event start 5 7
Related Book For
Accounting Information Systems
ISBN: 9780132871938
11th Edition
Authors: George H. Bodnar, William S. Hopwood
Posted Date: