4. Consider the following project activities: ACTIVITY A B C D DURATION (WEEKS) PREDECESSORS None 5 7 32 E 6 F 6 G 8
4. Consider the following project activities: ACTIVITY A B C D DURATION (WEEKS) PREDECESSORS None 5 7 32 E 6 F 6 G 8 H +P None B A, C B D D E, G