4. Given the following project and crash schedule: Time, days Cost, $ Activity Predecessor Normal Crash Normal Crash A 4 2 10,000 11,000 B
4. Given the following project and crash schedule: Time, days Cost, $ Activity Predecessor Normal Crash Normal Crash A 4 2 10,000 11,000 B A 3 2 6,000 9,000 C A 2 1 4,000 6,000 D A 5 3 14,000 18,000 E B 1 1 9,000 9,000 F C 3 2 7,000 8,000 G D 4 2 13,000 25,000 F,G 4 1 11,000 18,700 E,H 6 5 20,000 29,000 a. Draw the network for the project. b. Find the critical path c. Determine the minimum total time and corresponding cost