4 Mr Noppadon Muangkroot, Supply Manager of the Royal Thai Thermal Fuel Company (RTTFC) was reviewing a purchase requisition received from Department A of the

4

Mr Noppadon Muangkroot, Supply Manager of the Royal Thai Thermal Fuel Company (RTTFC) was reviewing a purchase requisition received from Department A of the company.

The requisition simply stated, "Buy a Tow Lift High Rise Forklift Truck, as per attached technical specification to be delivered by 1 June 2022."

Mr Noppadon was annoyed that, despite repeated reminders that requisitions should be comprehensive to enable effective procurement, the requisition that had been sent by Department A was quite incomplete.

He went up to the Head of Department A and said, "I need more information. I am sure that you are aware that the acquisition of equipment has a lot more involved than just the dollar value of the purchase."

Required:

  1. What does Mr Noppadon mean by saying, "I am sure that you are aware that the acquisition of capital equipment has a lot more involved than just the dollar value of the purchase?" Explain from a procurement/supply management perspective.
  2. What elements of costs would have to be considered when procuring capital equipment like a forklift truck?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Principles of Responsible Management Global Sustainability Responsibility and Ethics

Authors: Oliver Laasch

1st Edition

9781285981321, 1285080262, 1285981324, 978-1285080260

More Books

Students also viewed these General Management questions