4 The following information is available for a company's utility cost for operating its machines over the last four months. Month January Machine hours
4 The following information is available for a company's utility cost for operating its machines over the last four months. Month January Machine hours 1,080 February 1,980 00:57:25 March 2,760 April 780 Ask Utility cost $5,630 $7,260 $8,100 $3,960 Using the high-low method, the estimated variable cost per machine hour for utilities is: Multiple Choice $2.93. $5.08. $2.09. $3.78.